The short answer
Compare the allowance per square foot with the entered project cost per square foot. The allowance used is limited to the project cost, and the remaining gap stays visible instead of being treated as free rent.
Worked exampleA $40/SF allowance on 5,000 SF is $200,000; a $65/SF build-out is $325,000, leaving a $125,000 gap.
Common mistakes
- Calling an allowance cash in hand
- Ignoring project cost above the allowance
Limitations
Eligibility, work letters, and reimbursement conditions are outside the arithmetic model.
Use the assumption in context
Start with the relevant tool, preserve the source input, and keep the result alongside the proposal or budget it describes. A calculated result is only as reliable as the assumption and period entered.