The short answer
A later construction payment, delayed reimbursement, or rent step can make the cumulative cash requirement peak after month one. The planner reports both opening cash and the peak month.
Worked exampleA month-four TI reimbursement can leave month two as the peak even when opening cash is lower.
Common mistakes
- Looking only at the first invoice
- Ignoring cumulative cash
Limitations
No operating revenue or bank balance is inferred.
Use the assumption in context
Start with the relevant tool, preserve the source input, and keep the result alongside the proposal or budget it describes. A calculated result is only as reliable as the assumption and period entered.